UCHealth Longs Peak Hospital

Project Profile

UCHealth Longs Peak Hospital

Let’s Build

Partner with us on your next project.

Owner

UCHealth

Client

Haselden Construction

Size

220,000 sq ft

On this project, U.S. Engineering again teamed up with Haselden Construction. This established relationship played a part in the companies’ ability to successfully execute a fast-track schedule of only 18 months.

The team pre-manufactured corridor multi-trade racks and headwalls on-site, which allowed it to maintain the schedule and ensure a safer, cleaner work environment. Communication was key among all trades in order to complete the project on schedule..

MECHANICAL HIGHLIGHTS
  • 3 Air-cooled chillers
  • 1 Dry cooler
  • 7 Custom RTUs
  • 2 LPS boilers
  • 4 Heating water boilers
  • 5 Snowmelt Zones
  • Medical air compressor
  • Medical vacuum pump
  • RO/DI system